terça-feira, 21 de dezembro de 2010


STEP – 1 (THE SPACE)




FACTORY  - HOMEBLOWN EUROPE
LOCATION – CHARNECA DA CAPARICA, LISBON, PORTUGAL
SPACE – 270 m2,
APROXIMITY - 5km, to the Beach, and 15 Km to Lisbon
In April of 2009, Homeblown looks for a space, after looking over 10 spaces, in less than 1 month we sign the contract with the Landlaw, 270 m2, Industrial Space, 5 Km to Costa da Caparica and 15 KM to Lisbon. (Know the Planning of the factory starts).

.STEP – 2 (LAYOUTS)

 After a lot of work and conclusion, Homeblown Staff design a first layout for the new factory, regarding Machines, spaces around the factory.


The second layout, more important is the display of ELECTRICAL, WATER, AND AIR POINTS.
Everything is revised 3 to 4 times, and discussed about all the planning’s of the factory.
3 weeks later, the project is approved and now we are ready to start to put the factory UP.

STEP – 3 (IN CONSTRUCTION)


Thanks to Homeblown UK staff, Jonathan, Badger, Mister Oscar (WILDER), Joaquin Lino (Electrical Man) and the construction mans, we get thinks running, each man knows exactly what to do.

After 2 months, of hard working, including Saturdays and Sunday, finally the hard work in the factory is done.
Now we are ready to make the first test and project the first Surf Blanks.


Sem comentários:

Enviar um comentário